New Science Wing for Wapato Schools

modular science classroom

The first two modular components of the new High School Science Wing rolled into town this afternoon (Dec. 16th).   Four more are scheduled to arrive tomorrow and most of the rest are scheduled to arrive next week. There are 17 pieces in all that make up the building. They are being trucked over from the construction plant in Marysville, WA (Whitley-Evergreen). If the weather cooperates and they all arrive on schedule, a crane will be brought in the week of December 26th to lift them on to the foundation…Once the building is assembled on the foundation, crews will begin hooking up utilities and doing the interior and exterior finish work. The District hopes to take possession of the new Science Wing in early March.

Source:  Wapato School District